(a) The building permit fee for all construction within the town shall be computed based
on the following table:
Cost of Construction
Fee
$500.00—$3,000.00
$30.00
$3,001.00—$25,000.00
$69.25 for the first $3,000.00 plus $0.014 for each additional amount up to and including
$25,000.00
$25,001.00—$50,000.00
$391.25 for the first $25,000.00 plus $0.0101 for each additional amount up to and
including $50,000.00
$50,001.00—$100,000.00
$643.75 for the first $50,000.00 plus $0.007 for each additional amount up to and
including $100,000.00
$100,001.00—$500,000.00
$993.75 for the first $100,000.00 plus $0.0056 for each additional amount up to and
including $500,000.00
$500,001.00—$1,000,000.00
$3,233.75 for the first $500,000.00 plus $0.00475 for each additional amount up to
and including $1,000,000.00
$1,000,001.00 and up
$5,608.75 for the first $1,000,000.00 plus $0.00315 for each additional amount
Other Inspections
Fees
1.
Inspection outside of normal business hours
$47.00 per hour, minimum charge 2 hours
2.
Reinspection fees per section 305.8
$47.00 per hour
3.
Inspections for which no fee is set
$47.00 per hour, minimum charge ½ hour
4.
Additional plan review for revisions
$47.00 per hour, minimum charge ½ hour
5.
For use of outside consultants
Actual costs
6.
Occupancy fee
$30.00
7.
Structure moving permit 600 sf or more
$45.00
8.
Excavation permit
$50.00
9.
Driveway, curb cut
$50.00
(b) Upon issuance of a building permit, separate plumbing, electrical, and mechanical
permits shall also be issued at no additional fee for the plumbing, electrical and
mechanical work contained in the construction designated in the building permit.