§ 14-80. Building permit fees  


Latest version.
  • (a) The building permit fee for all construction within the town shall be computed based on the following table:

    Cost of Construction Fee
    $500.00—$3,000.00 $30.00
    $3,001.00—$25,000.00 $69.25 for the first $3,000.00 plus $0.014 for each additional amount up to and including $25,000.00
    $25,001.00—$50,000.00 $391.25 for the first $25,000.00 plus $0.0101 for each additional amount up to and including $50,000.00
    $50,001.00—$100,000.00 $643.75 for the first $50,000.00 plus $0.007 for each additional amount up to and including $100,000.00
    $100,001.00—$500,000.00 $993.75 for the first $100,000.00 plus $0.0056 for each additional amount up to and including $500,000.00
    $500,001.00—$1,000,000.00 $3,233.75 for the first $500,000.00 plus $0.00475 for each additional amount up to and including $1,000,000.00
    $1,000,001.00 and up $5,608.75 for the first $1,000,000.00 plus $0.00315 for each additional amount

     

    Other Inspections Fees
    1. Inspection outside of normal business hours $47.00 per hour, minimum charge 2 hours
    2. Reinspection fees per section 305.8 $47.00 per hour
    3. Inspections for which no fee is set $47.00 per hour, minimum charge ½ hour
    4. Additional plan review for revisions $47.00 per hour, minimum charge ½ hour
    5. For use of outside consultants Actual costs
    6. Occupancy fee $30.00
    7. Structure moving permit 600 sf or more $45.00
    8. Excavation permit $50.00
    9. Driveway, curb cut $50.00

     